PROGRESS OF WORK:
– PILOT: Executed 507 piles that correspond to Tower 1 and 2 and an important part of the Square. Pilot projects finish in December this year.
– FOUNDATION: Run the foundation of Tower 1, and a part of the square
– Structure: the structure has been executed in Tower 1 which corresponds to the walls from the basement to the floor 1 and floor plate 1. To make the structure is being completed Outinor assembling the formwork, which is ready in the next week.
It is planned to finish the structure of Tower 1 in the month of January 2016.
– RETAINING WALLS: Run the corresponding to the square in the city east and west of Tower 1
photos showing the progress of work is attached. Attached photos of the construction progress. Remember that from now on we will be updating photos of progress on our website in the «percentage of completion» section found within this project.
STATE SALES:
To date 73 properties are sold Cortijo Cajicá and dynamics of sales is generally favorable.
FRIENDS CLUB AWARDS:
Remember our awards program CLUB OF FRIENDS is in force and that their referrals for Cortijo de Cajicá you can get $ 400,000 for each effective referral and an additional ticket for the draw of all the furniture and decoration of the model apartment Cortijo.