SALES: It is sold 78% of the project, leaving only 19 apartments to sell. We invite all buyers of the project to refer their family and friends to end the sale of all of the units that comprise it .
Remember that at the project site have enabled sales room is open every day from 9:00 a.m a 6:00 p.m. continuous day.
This photo of the facade of the lot with the salesroom
FINANCING: Construction of the project is financed by BBVA, who has already made two disbursements credit builder and has made us an excellent deal at the level of interest rates and credit conditions for buyers of Ambroxía Casa Boutique .
ADVANCE WORK: The work is finishing one of the most complex parts of its execution is to complete the excavation of 3 basements and melted the perimeter walls. So that the detailed progress is:
EARTHWORKS: 97%
PRELIMINARY ACTIVITIES: 82%
FOUNDATIONS: 64%
STRUCTURE: 28%
RETAINING WALLS: 95%
The whole foundation of the project is scheduled for completion on Saturday 28 May, 2016. Currently the activity of the basement columns 3 began, with a view to start with the construction of the first plate corresponding to the basement mezzanine 2 on Monday May 23, 2016.
It is scheduled to reach the zero level of the structure (basement – level next via the second week of August 2016.
The programming will allow us to start deliveries to our customers at the end of September 2017.
Here you can see photos of the progress of work of Ambroxía Casa Boutique :
AWARDS FOR REFERRALS:
Remember to Win with Phoenix is very easy, as reward for all referrals who purchase our projects, in the case ofAmbroxía House Boutique you can win:
For more information and advice please contact:
Ambroxia Casa Boutique Cra 28 # 44-66 Sotomayor
Grand Boulevard: Boulevard Bolivar with 20 career
S.C. Megamall Local 228
Tel: (7) 6353636 to 6439990 – 6431010
Mobile: 310 554 6588/315 354 7671